Safety
Welding equipment inspection checklist
The arc welder’s check before starting: machine hook-up, work lead and clamp, frame ground, cable insulation and splices, electrode holder, leaks, the disconnect switch and the manufacturer’s instructions, following OSHA 1910.254(d).
- How often
- Before each use
- Who
- Welder
- Time
- About 5 min
- Items
- 22
Download this checklist
Free, no sign-up
Have your own paper version? A photo of it is enough for Vardian AI to draft the form. Photo-to-form →
Before you use it
- OSHA 29 CFR 1910.254(d) covers the operation and maintenance of arc welding equipment. Before starting operations, all connections to the machine are checked to make certain they are properly made, the work lead is firmly attached to the work, magnetic work clamps are freed of adherent spatter on their contact surfaces, and coiled welding cable is spread out before use to avoid serious overheating and damage to the insulation (1910.254(d)(2)). Grounding of the machine frame is checked, with special attention to the safety ground connections of portable machines ((d)(3)); there must be no leaks of cooling water, shielding gas or engine fuel ((d)(4)); and proper switching equipment for shutting down the machine must be provided ((d)(5)).
- Cables with splices within 10 feet (3 m) of the holder may not be used ((d)(8)). Cables with damaged insulation or exposed bare conductors are replaced, and lengths of work and electrode cable are joined only with connecting means specifically intended for the purpose, insulated for the service conditions ((d)(9)(iii)). Electrode holders not in use are placed so they cannot make electrical contact with persons, conducting objects, fuel or compressed gas tanks ((d)(7)). A machine that has become wet is thoroughly dried and tested before it is used ((d)(9)(ii)).
- Under (d)(9)(i), the operator should report any equipment defect or safety hazard to the supervisor, and use of the equipment is discontinued until its safety has been assured; repairs are made only by qualified personnel. Workers assigned to operate or maintain arc welding equipment must be acquainted with 1910.254 and with 1910.252(a), (b) and (c) ((d)(1)), and the manufacturer’s printed rules and instructions are strictly followed ((d)(6)).
- Installation items that the walk-up can see: a disconnecting switch or controller at or near each machine that has none mounted as an integral part ((c)(3)(i)); the frame or case grounded, except on engine-driven machines ((c)(2)(i)); chains, wire ropes, cranes, hoists and elevators never used to carry welding current ((c)(2)(iii)); conduits not used to complete a work-lead circuit, and pipelines not used as a permanent part of one ((c)(2)(ii)); control apparatus enclosed except for operating wheels, levers or handles, and input power terminals and live parts completely enclosed and accessible only by means of tools ((b)(4)(ii)–(iii)).
- OSHA sets no interval for this check beyond “before starting operations”, so run it per machine before each job or shift. The fire precautions for the welding itself, such as the 35-foot clearance, the fire watch and the permit, are in 1910.252(a) and in our hot work permit template.
Machine
- 1Checkpoint scan
Scan the tag on the welding machine
- 2Note
Machine identifier and work location
- 3Choice
Machine type
Transformer (a.c.) · Rectifier or inverter (d.c.) · Engine-driven · Multi-process
Hook-up and grounding (1910.254(d)(2)–(3), (c)(2))
- 4Pass / fail
All connections to the machine checked and properly made
- 5Pass / fail
Work lead firmly attached to the work; magnetic clamp contact surfaces free of spatter
- 6Pass / fail
Machine frame or case grounded; on a portable machine, the safety ground connection checked
- 7Pass / fail
No chain, wire rope, crane, hoist, elevator, conduit or pipeline carrying welding current
- 8Pass / fail
Coiled welding cable spread out before use
Cables and electrode holder (1910.254(d)(7)–(9), (b)(4)(iv))
- 9Pass / fail
Electrode and work cable insulation undamaged; no exposed bare conductors
- 10Pass / fail
No splice within 10 ft (3 m) of the electrode holder; cable joints made with connectors intended for the purpose
- 11Pass / fail
Electrode holder insulation intact; holder parked where it cannot touch persons, conducting objects, fuel or gas cylinders
- 12Pass / fail
Welding lead terminals on the machine protected from accidental contact
- 13Photo
Photo of the cables, clamp and holder
Machine condition (1910.254(d)(4)–(6), (d)(9)(ii), (b)(4), (c)(3))
- 14Pass / fail
No leaks of cooling water, shielding gas or engine fuel
- 15Pass / fail
Disconnecting switch or controller at or near the machine, and it works
- 16Pass / fail
Control apparatus enclosed; input terminals and live parts enclosed and accessible only with tools
- 17Pass / fail
Machine dry; if it has been wet, dried and tested before use
- 18Pass / fail
Machine suited to the conditions here (corrosive fumes, humidity, oil vapor, flammable gas, vibration, dust, weather)
- 19Pass / fail
Manufacturer’s operating instructions available and followed
Result
- 20Choice
Result
Safe to use · Defect found: taken out of service and reported
- 21Note
Defect and action taken
- 22Signature
Welder
References
Download this checklist
Free, no sign-up
Read more
Field types in this template
- Checkpoint scan
- Note
- Choice
- Pass / fail
- Photo
- Signature
In Vardian, readings are checked against their limits as they are entered, and photos and signatures attach to the check itself.
From the sheet to the round
Build a template as a Vardian form, and each line becomes a checkpoint that knows its limit.
Animation: a paper checklist line, compressor discharge pressure with a blank for the reading in bar, becomes a Vardian checkpoint with a limit of 7.0 to 8.5 bar. Scanning the compressor's NFC tag verifies the checkpoint, a reading of 9.1 bar is flagged out of range, and a work order is created from it.
Run this checklist on the round