Safety
Extension cord and GFCI inspection checklist
The before-use check of extension cords and cord-and-plug equipment that OSHA 1910.334(a)(2) requires on any shift, with a GFCI test and the grounding conductor checks of an assured equipment grounding conductor program.
- How often
- Before use on each shift, and when a cord or tool is relocated
- Who
- Person using the equipment, or the competent person for the grounding program
- Time
- About 5 min
- Items
- 17
Download this checklist
Free, no sign-up
Have your own paper version? A photo of it is enough for Vardian AI to draft the form. Photo-to-form →
Before you use it
- OSHA 29 CFR 1910.334(a)(2) requires portable cord- and plug-connected equipment and extension cords to be visually inspected before use on any shift for external defects, such as loose parts, deformed and missing pins, or damage to the outer jacket or insulation, and for evidence of possible internal damage, such as a pinched or crushed outer jacket. Items that stay connected once in place and are not exposed to damage need not be inspected until they are relocated. A defective or damaged item is removed from service until the repairs and tests that make it safe have been made.
- Under 1910.304(b)(3)(ii), during construction-like activities, including certain maintenance, remodeling or repair work, 125-volt, single-phase 15-, 20- and 30-ampere receptacle outlets that are not part of the permanent wiring and are in use by personnel need ground-fault circuit-interrupter protection; the cord connector of an extension cord used for temporary power counts as a receptacle outlet. Where GFCI protection is not available for other receptacles, an assured equipment grounding conductor program applies: a visual inspection before each day’s use, and grounding conductor tests before first use, after repairs or suspected damage, and at intervals not exceeding 3 months (6 months for cord sets and receptacles that are fixed and not exposed to damage), with a record of each test.
- A flexible cord used with grounding-type equipment contains an equipment grounding conductor, and plugs, receptacles and adapters are not altered or used in a way that interrupts its continuity (1910.334(a)(3)). Cords are not used to raise or lower equipment or fastened with staples (1910.334(a)(1)). Test each GFCI as its manufacturer instructs.
Cord or equipment
- 1Checkpoint scan
Scan the cord or tool tag
- 2Note
Cord set or equipment ID
- 3Choice
Item
Extension cord · Cord-and-plug tool or equipment · Portable GFCI or cord set with GFCI
Visual inspection
- 4Pass / fail
Outer jacket and insulation undamaged: no cuts, abrasion or exposed conductors
- 5Pass / fail
No pinched or crushed jacket that could hide internal damage
- 6Pass / fail
Plug and connector bodies not cracked, loose or missing parts
- 7Pass / fail
Pins straight and present, including the grounding pin
- 8Pass / fail
Cord for grounding-type equipment has an equipment grounding conductor
- 9Pass / fail
Not fastened with staples, hung so as to damage the jacket, or used to raise or lower equipment
- 10Pass / fail
Approved for the location where it is wet or conductive
GFCI and grounding
- 11Pass / fail
GFCI protection in place for temporary power during construction-like work
- 12Pass / fail
GFCI trips on its test button and resets
- 13Pass / fail
Plug and receptacle configurations match; no adapter that interrupts the ground
- 14Reading· months
Months since the last grounding conductor test, under an assured grounding program
Not more than 3 months; 6 months for cord sets and receptacles that are fixed and not exposed to damage.
Result
- 15Choice
Result
Fit for use · Removed from service
- 16Photo
Photo of any defect
- 17Signature
Inspected by
Download this checklist
Free, no sign-up
Read more
Field types in this template
- Checkpoint scan
- Note
- Choice
- Pass / fail
- Reading
- Photo
- Signature
In Vardian, readings are checked against their limits as they are entered, and photos and signatures attach to the check itself.
From the sheet to the round
Build a template as a Vardian form, and each line becomes a checkpoint that knows its limit.
Animation: a paper checklist line, compressor discharge pressure with a blank for the reading in bar, becomes a Vardian checkpoint with a limit of 7.0 to 8.5 bar. Scanning the compressor's NFC tag verifies the checkpoint, a reading of 9.1 bar is flagged out of range, and a work order is created from it.
Run this checklist on the round
We'll set it up in Vardian with your checkpoints and limits during a demo.