Safety

Extension cord and GFCI inspection checklist

The before-use check of extension cords and cord-and-plug equipment that OSHA 1910.334(a)(2) requires on any shift, with a GFCI test and the grounding conductor checks of an assured equipment grounding conductor program.

How often
Before use on each shift, and when a cord or tool is relocated
Who
Person using the equipment, or the competent person for the grounding program
Time
About 5 min
Items
17
Set it up in Vardian

Have your own paper version? A photo of it is enough for Vardian AI to draft the form. Photo-to-form →

Before you use it

  • OSHA 29 CFR 1910.334(a)(2) requires portable cord- and plug-connected equipment and extension cords to be visually inspected before use on any shift for external defects, such as loose parts, deformed and missing pins, or damage to the outer jacket or insulation, and for evidence of possible internal damage, such as a pinched or crushed outer jacket. Items that stay connected once in place and are not exposed to damage need not be inspected until they are relocated. A defective or damaged item is removed from service until the repairs and tests that make it safe have been made.
  • Under 1910.304(b)(3)(ii), during construction-like activities, including certain maintenance, remodeling or repair work, 125-volt, single-phase 15-, 20- and 30-ampere receptacle outlets that are not part of the permanent wiring and are in use by personnel need ground-fault circuit-interrupter protection; the cord connector of an extension cord used for temporary power counts as a receptacle outlet. Where GFCI protection is not available for other receptacles, an assured equipment grounding conductor program applies: a visual inspection before each day’s use, and grounding conductor tests before first use, after repairs or suspected damage, and at intervals not exceeding 3 months (6 months for cord sets and receptacles that are fixed and not exposed to damage), with a record of each test.
  • A flexible cord used with grounding-type equipment contains an equipment grounding conductor, and plugs, receptacles and adapters are not altered or used in a way that interrupts its continuity (1910.334(a)(3)). Cords are not used to raise or lower equipment or fastened with staples (1910.334(a)(1)). Test each GFCI as its manufacturer instructs.

Cord or equipment

  1. 1

    Scan the cord or tool tag

    Checkpoint scan
  2. 2

    Cord set or equipment ID

    Note
  3. 3

    Item

    Extension cord · Cord-and-plug tool or equipment · Portable GFCI or cord set with GFCI

    Choice

Visual inspection

  1. 4

    Outer jacket and insulation undamaged: no cuts, abrasion or exposed conductors

    Pass / fail
  2. 5

    No pinched or crushed jacket that could hide internal damage

    Pass / fail
  3. 6

    Plug and connector bodies not cracked, loose or missing parts

    Pass / fail
  4. 7

    Pins straight and present, including the grounding pin

    Pass / fail
  5. 8

    Cord for grounding-type equipment has an equipment grounding conductor

    Pass / fail
  6. 9

    Not fastened with staples, hung so as to damage the jacket, or used to raise or lower equipment

    Pass / fail
  7. 10

    Approved for the location where it is wet or conductive

    Pass / fail

GFCI and grounding

  1. 11

    GFCI protection in place for temporary power during construction-like work

    Pass / fail
  2. 12

    GFCI trips on its test button and resets

    Pass / fail
  3. 13

    Plug and receptacle configurations match; no adapter that interrupts the ground

    Pass / fail
  4. 14

    Months since the last grounding conductor test, under an assured grounding program

    Not more than 3 months; 6 months for cord sets and receptacles that are fixed and not exposed to damage.

    Reading· months

Result

  1. 15

    Result

    Fit for use · Removed from service

    Choice
  2. 16

    Photo of any defect

    Photo
  3. 17

    Inspected by

    Signature

Field types in this template

  • Checkpoint scan
  • Note
  • Choice
  • Pass / fail
  • Reading
  • Photo
  • Signature

In Vardian, readings are checked against their limits as they are entered, and photos and signatures attach to the check itself.

From the sheet to the round

Build a template as a Vardian form, and each line becomes a checkpoint that knows its limit.

Animation: a paper checklist line, compressor discharge pressure with a blank for the reading in bar, becomes a Vardian checkpoint with a limit of 7.0 to 8.5 bar. Scanning the compressor's NFC tag verifies the checkpoint, a reading of 9.1 bar is flagged out of range, and a work order is created from it.

Run this checklist on the round

We'll set it up in Vardian with your checkpoints and limits during a demo.