Inspections

Air receiver and compressed air system inspection checklist

The routine check of a compressed air receiver and its system against OSHA 1910.169(b): access to drains and manholes, draining, the pressure gauge, the safety valve and nothing between it and the tank, with a pressure reading and a leak walk.

How often
Weekly, or at the interval your site sets
Who
Maintenance technician or operator
Time
About 10 min
Items
19
Set it up in Vardian

Have your own paper version? A photo of it is enough for Vardian AI to draft the form. Photo-to-form →

Before you use it

  • OSHA 29 CFR 1910.169(b) requires every air receiver to be installed so that all drains, handholes and manholes are easily accessible, and never buried underground or located in an inaccessible place; to have a drain pipe and valve at its lowest point, with the receiver completely drained frequently enough to prevent excessive liquid from accumulating; and to have a readily visible indicating pressure gauge and one or more spring-loaded safety valves.
  • Under 1910.169(b)(3), the safety valves’ total relieving capacity keeps receiver pressure from exceeding the maximum allowable working pressure by more than 10 percent; no valve of any type is placed between the receiver and its safety valves; safety appliances are installed so that they cannot readily be made inoperative, including by the elements; and all safety valves are tested frequently and at regular intervals. OSHA sets no fixed interval for draining or valve testing, so take both from the manufacturer’s instructions.
  • New receivers are built to the ASME Boiler and Pressure Vessel Code, Section VIII, and safety valves are constructed, installed and maintained to it (1910.169(a)(2)). Record the maximum allowable working pressure from the nameplate and set the pressure limits from it.

Receiver

  1. 1

    Scan the receiver tag

    Checkpoint scan
  2. 2

    Nameplate legible, with the maximum allowable working pressure

    Pass / fail
  3. 3

    Drains, handholes and manholes easily accessible

    Pass / fail
  4. 4

    Shell, supports and connections free of visible corrosion, dents and leaks

    Pass / fail

Gauge and safety valve

  1. 5

    Pressure gauge readily visible and readable

    Pass / fail
  2. 6

    Receiver pressure

    Set the limits from the manufacturer’s manual and your normal operating range.

    Reading· psi or bar
  3. 7

    Spring-loaded safety valve fitted, with no valve between it and the receiver

    Pass / fail
  4. 8

    Safety valve and controls not obstructed, gagged or otherwise made inoperative

    Pass / fail
  5. 9

    Safety valve tested at its scheduled interval

    Pass / fail
  6. 10

    Date of the last safety valve test

    Note

Drain

  1. 11

    Drain valve at the lowest point opened and the receiver completely drained

    Pass / fail
  2. 12

    Liquid drained

    None · Normal · Excessive: shorten the drain interval

    Choice
  3. 13

    Automatic drain trap, where fitted, discharging

    Pass / fail

System

  1. 14

    No audible air leaks at lines, hoses and fittings

    Pass / fail
  2. 15

    Hoses and couplings undamaged and secured

    Pass / fail
  3. 16

    Dryer and filters, where fitted, working and drained

    Pass / fail

Result

  1. 17

    Result

    Safe to operate · Removed from service

    Choice
  2. 18

    Photo of any defect

    Photo
  3. 19

    Inspected by

    Signature

Field types in this template

  • Checkpoint scan
  • Pass / fail
  • Reading
  • Note
  • Choice
  • Photo
  • Signature

In Vardian, readings are checked against their limits as they are entered, and photos and signatures attach to the check itself.

From the sheet to the round

Build a template as a Vardian form, and each line becomes a checkpoint that knows its limit.

Animation: a paper checklist line, compressor discharge pressure with a blank for the reading in bar, becomes a Vardian checkpoint with a limit of 7.0 to 8.5 bar. Scanning the compressor's NFC tag verifies the checkpoint, a reading of 9.1 bar is flagged out of range, and a work order is created from it.

Run this checklist on the round

We'll set it up in Vardian with your checkpoints and limits during a demo.